Utah State University Logo

USU Facilities

24Jul2014

Enchanted Modernities - Mysticism, Landscape & the American West

Caine College of the Arts and the Leverhulme Trust…

24Jul2014

Wayne Gardening Club

Meet behind the Courthouse in Loa, Ut. We will be…

24Jul2014

A Funny Thing Happened On The Way To The Forum - OLRC Stage Production

The fast-paced, witty, irreverent comedy is one of the…

25Jul2014

Artisan Aggie Cheese Tasting

Artisan Aggie Cheese tasting & video presentation…

25Jul2014

Tons of Money -- Lyric Rep Stage Production

This spirited farce follows a broke inventor who inherits…

More events

Announcements (Outages/Shut-downs)

May 26, 2014-Ongoing
HPER Occupants: Beginning the week of May 26, a safety fence, construction barricades and overhead protection will begin in preparation for the roof project. The work will include the upper roof over the basketball courts, gymnastic room and exercise rooms. It will also include the offices spaces on the south side of the building. NO WORK WILL BE DONE OVER THE SWIMMING POOLS. The tear-off work is expected to be very dusty and noisy, especially in the second floor areas. The contractor will install coverings within these rooms to control dust and damage to the building contents. The contractor has prepared a schedule which allows for basketball camps and other major events within the building. These events should not be interrupted but noise will be a continual concern. No excessive smells from glues and/or solvents are expected, but they will still be monitored closely. Actual work on the roof is scheduled to begin the first week in June. Project completion is expected in mid-August.
June 11, 2014-Ongoing
Student Health & Wellness Center: On June 16, a reroofing project will begin on the Student Health & Wellness Center and is expected to continue through August and potentially into September. The project will involve the removal and replacement of the existing roof membrane and its gravel ballast as well as the large skylights. No shutdowns of rooftop equipment or power supplies are anticipated at this time but notices will be sent out ahead of schedule if it becomes necessary to do so.

As part of this project, fences and covered walkways will be installed around the perimeter of the building (beginning June 11) which are to provide fall protection for building users and occupants as old materials are removed and the new is installed. All building exits required for emergency egress will be maintained open. Building materials and dumpsters will also be moved onto the site and stored there but parking interruption will be very minor.

As the project moves along, building occupants should expect loud noises, dust, and minor interferences with business as usual. The contractor will strive to limit dust entry into the building and will make efforts to support the needs of work going on within the building. However, there will at times be some slight interruptions.  Also to be expected is some off-gassing of glues and solvents as the roof membrane is attached to the roof structure and seams are glued. The contractor will make every effort to reduce the infiltration of odors into the building but they cannot be eliminated completely. Therefore, MSDS sheets for these chemical products are available upon request for those who may be sensitive to them or who may have concerns.  

All users of the building - as well as the outdoor track and field - are requested at this time to please remove all equipment from the roof such as tanks, tubs, athletic equipment, etc. Please note! After the roofing project is complete, NO extraneous equipment will be allowed on the roof!  All equipment used for track events must be kept on the field or stored elsewhere and any access to the roof by individuals is prohibited unless a roof access permit is obtained from Facilities. This is due to the fact that membrane roofs are highly susceptible to puncturing and can be expensive to repair, plus the inherent potential for damaging expensive research and equipment within a building.

If you have any questions or concerns regarding the project, please contact Quin Whitaker at 797-8064. Thank you!
July 14, 2014-Ongoing
Biotech Occupants: On MONDAY, JULY 14 AND FOR APPROXIMATELY 2-3 WEEKS, THE ELEVATOR IN THE BIOTECH BUILDING WILL BE SHUT-DOWN.  During this time there will be no access to the elevator.  This shut-down is necessary in order to complete needed elevator upgrades. Please plan accordingly.
July 17-23, 2014
Ray B West Occupants: Facilities Technicians will be installing new dampers and making zone damper modifications to the mechanical systems for the Ray B West Building. While these installations and modifications are taking place it will be necessary to turn fan systems off. See below for the shut-down schedule:
July 17 & 21, 1st & 2nd Floors
July 18, 3rd Floor
July 22 & 23, 4th Floor
All shut-downs will be from 7am until 4:30pm. During these dates and times there will be no airflow or air conditioning to the rooms on the above listed floors. Fan systems will be running thru the night hours to help cool the core of the building during this time.
July 23, 2014
Ray B. West, Family Life, WW Lundberg and Gun Shed Building Occupants: On Wednesday, July 23, from 12:30-3:30PM, the STEAM TO RAY B. WEST, FAMILY LIFE, WW LUNDBERG & GUN SHED WILL BE TURNED OFF.  During this time there will be no hot water or heatingJ in the buildings. Please plan accordingly.
July 25, 2014
Wayne Estes Occupants: On Friday, July 25 from 5:30am until 7:30am, the power to the building will be turned-off. During this time there will be no lighting (except for E-power) in the building. Please plan accordingly. Thank you for your cooperation!
August 1, 2014-Ongoing
NFS Occupants: Starting on August 1, 2014 and continuing for 2-3 weeks, the elevator in the NFS Building will be shut-down. During this time there will be no access to the elevator. This shut-down is necessary in order to complete needed elevator upgrades. Please plan accordingly. Thank you for your cooperation!
August 5, 2014-Ongoing
Animal Science Occupants: Starting on Tuesday, August 5 and continuing for 2-3 weeks, the elevator in the Animal Science Building will be shut-down. During this time there will be no access to the elevator. This shut-down s necessary in order to complete needed elevator upgrades. Please plan accordingly. Thank you for your cooperation!
August 8, 2014
BNR Occupants: Friday, August 8, 2014, from 6:00am until noon, the fan system that serves rooms 230 thru 342 in the BNR will be shut down. This is a necessary outage to replace fan drives and motors. This repair will help with the low air flow issues that some of the rooms of the BNR building have been experiencing this summer. During this time there will be no air conditioning or ventilation. Please plan accordingly.
May 3-10, 2015
The annual steam shut-down will be held from May 3-May 10, 2015. This means there will be no central steam for processes, water heating, showers and cooking. Please mark your calendars and plan accordingly.
If you have any questions or concerns, please contact Facilities Customer Service.
Phone: 797-3535
Phone: 797-1947
Email: facilitiescustserv@usu.edu