Facilities serves Utah State University by providing an environment for education, innovative learning, and its application in the worldwide community.
Outages & Shutdowns
Outage and shutdown information is updated as it becomes available. Unless otherwise listed, please call Facilities, Customer Service at 435-797-3535 or 435-797-1947 with any questions or concerns.
Current
Old Main Building
March 23 to August 31, 2026
Old Main Construction
The continuance of the Old Main piping replacement project taking place this spring/summer. This project will continue repairs to some of the heating water, and cooling water pipes in the building, as well as the addition of isolation valves for some other plumbing fixtures. Much of the work will take place in mechanical rooms, pipe chases, and corridor ceilings of the building. We expect most impacts to the building occupants to be experienced in the corridors, but some departmentally assigned spaces could also be affected. In addition to construction areas in the corridors, some temporary shutdowns of water, heating, and cooling systems may be necessary. Utility outage notices will be sent out prior to any outage. Below is a list of impacts to expect during this project.
- Preparation for the piping replacement will begin on March 23rd. You will begin to see contractors in the hallways and accessing ceilings. The following Monday - March 30th, piping replacement will begin in earnest.
- Construction is planned between March 23rd and August 31st.
- Construction will occur mainly in the hallways of the building. This means you may encounter places where part of the hallway is blocked off. The contractor will maintain access around the work wherever possible.
- It is possible that doors may be blocked occasionally, if work is taking place overhead.
- Construction will move through the building to those locations where the piping needs to be replaced. Please expect a shifting work site as the project progresses. Some locations where work can be expected are in the basement and first floor hallways, as well as some piping chase locations that may need to be accessed near your work areas.
- Please expect construction noise and smells in the building. This work includes welding and the associated smells. We are doing whatever we can to minimize the disruptions to the building occupants, but due to the extensive nature of this project, some noise and smells will be unavoidable.
- Air temperature controls in the building will be limited throughout the duration of the project. It could be cooler than comfortable for some employees, and warmer than comfortable at times. We are working to limit these impacts as much as possible.
1400 North
Friday, March 20 to Friday, April 24, 2026
Road Construction
Beginning Friday, March 20, 2026, construction on the 1400 North roadway, just adjacent to the new Vet Med Education building will begin. Traffic control signage and traffic barrels will be placed to direct traffic appropriately around the construction limits on the road. There may be traffic delays at times. The estimates completion date for this construction is Friday, April 24, 2026.
Please note that this is not a road closure. There will still be access for all thru traffic.
Please note that this is not a road closure. There will still be access for all thru traffic.
700 N (Aggie Boulevard)
Monday, April 6, 2026 - Monday, April 27, 2026
Construction
Beginning Monday, April 6, 2026, construction crews will start slip lining the irrigation line along 700 North (Aggie Boulevard). This will require sections of the road between the main pedestrian light/crossing and 1200 East to be one-lane traffic (see attached map). Contractors will have flaggers on each end of the sections to allow traffic to take turns moving from east to west in both directions. Individuals using 700 North should expect delays. The duration for this is anticipated to be 3 weeks.
This is necessary to prepare for the upcoming construction of this section of 700 North that will begin the week after commencement. More information on that project will be sent out at a later date.
View Construction Map
This is necessary to prepare for the upcoming construction of this section of 700 North that will begin the week after commencement. More information on that project will be sent out at a later date.
View Construction Map
Upcoming
Vet Science & LARC Buildings
Tuesday, April 14th, 2026
Power Shutdown
Scheduled for Tuesday, April 14th, 2026, our electricians will be shutting off the power in Vet Science and LARC buildings from 6:30 a.m- 7:00 a.m. All power will be down during this time to test the emergency power.
Engineering Building
Thursday, April 16, 2026
Fire Sprinkler Outage
Facilities technicians will shut off the building's fire sprinklers from 8:00 am to 12:00 pm to move a sprinkler. Consequently, fire sprinklers will not work during this time. Daily operations should not be affected.
USU
Sunday, May 3, 2026 - Sunday, May 10, 2026
2026 Steam Shutdown
This utility shut-off is done to provide necessary maintenance to our steam tunnel/utility systems throughout the USU Logan Campus.
During this week, there will be no steam, hot water, or heat to buildings on the central steam system. Please plan accordingly.
During this week, there will be no steam, hot water, or heat to buildings on the central steam system. Please plan accordingly.