USU Facilities

Facilities serves Utah State University by providing an environment for education, innovative learning, and its application in the worldwide community.

Outages & Shutdowns

Outage and shutdown information is updated as it becomes available. Unless otherwise listed, please call Facilities, Customer Service at 435-797-3535 or 435-797-1947 with any questions or concerns.

Current

Huntsman Hall
May 21, 2026 - Until Resolved

Urgent Bathroom Closure Notice

It was discovered today that the sewage pump in the basement of Huntsman Hall is not functioning correctly. There is a contractor who will be coming in tomorrow morning to help resolve this issue. Because of this, all basement bathrooms in the Huntsman Hall building are closed and are unusable during this time and until the issue is resolved. 

BNR Building
May 19, 2026 - Until Resolved

AC/Cooling Shutdown

Due to a broken fan bearing in one of the supply fans within the building, there is currently no cooling within the BNR building. Please see below for a list of areas affected. Repair parts are being ordered, but the time it will take for them to ship is estimated to be 1-2 weeks, if not longer. Consequently, there will be no cooling in this area of the building during this time. We are hopeful to get it up and running by the end of next week, but the actual repair time will depend on the shipping time of each replacement part.

Engineering Lab
April 15 - June 30, 2026

Building Survey & Inspection

Beginning Wednesday, April 15, 2026, contractors will begin conducting a building-wide materials survey of the Engineering Lab Building. Inspectors will conduct a visual and sample-based assessment of common areas, mechanical spaces, and where necessary, individual units, offices, and labs. Access to specific areas may be required. Access notice will be provided at least 24/48-hour notice before entering any occupied space. If you have specific scheduling needs or concerns, please contact Brayden George at brayden.george@usu.edu or 435-797-3770.

Old Main Building
March 23 to August 31, 2026

Old Main Construction

The continuance of the Old Main piping replacement project taking place this spring/summer. This project will continue repairs to some of the heating water, and cooling water pipes in the building, as well as the addition of isolation valves for some other plumbing fixtures.  Much of the work will take place in mechanical rooms, pipe chases, and corridor ceilings of the building.  We expect most impacts to the building occupants to be experienced in the corridors, but some departmentally assigned spaces could also be affected.  In addition to construction areas in the corridors, some temporary shutdowns of water, heating, and cooling systems may be necessary. Utility outage notices will be sent out prior to any outage.  Below is a list of impacts to expect during this project.

  • Preparation for the piping replacement will begin on March 23rd.  You will begin to see contractors in the hallways and accessing ceilings.  The following Monday - March 30th, piping replacement will begin in earnest.
  • Construction is planned between March 23rd and August 31st.  
  • Construction will occur mainly in the hallways of the building. This means you may encounter places where part of the hallway is blocked off.  The contractor will maintain access around the work wherever possible.
  • It is possible that doors may be blocked occasionally, if work is taking place overhead.  
  • Construction will move through the building to those locations where the piping needs to be replaced.  Please expect a shifting work site as the project progresses.  Some locations where work can be expected are in the basement and first floor hallways, as well as some piping chase locations that may need to be accessed near your work areas.
  • Please expect construction noise and smells in the building.  This work includes welding and the associated smells. We are doing whatever we can to minimize the disruptions to the building occupants, but due to the extensive nature of this project, some noise and smells will be unavoidable.
  • Air temperature controls in the building will be limited throughout the duration of the project.  It could be cooler than comfortable for some employees, and warmer than comfortable at times.  We are working to limit these impacts as much as possible.

Engineering Building
Sunday, May 3, 2026 - Monday, June 22, 2026

Heat Shutdown

Facilities technicians will be shutting off the heat to the building. There will be no heat for 6 weeks to replace bad gaskets throughout the building. There will be hot water but no heat to the building.

Student Health and Wellness Center North Parking Lot
Monday, May 4 - June, 2026

Parking Lot Repave

Beginning Monday, May 4, 2026 and running through June 2026, the north parking lot adjacent to the Student Health & Wellness building will begin to be replaced.
Parking Paving Project and Construction Staging Area set to be adjacent to the north of the Student Health and Wellness Center.

Lundberg Building
Monday, May 4 - Mid July, 2026

Window Replacement

Beginning Monday, May 4, 2026, Facilities Planning & Design and associated contractors will begin abating and removing windows throughout the Lundberg building. Temporary window covering will be provided for weather protection while this project is ongoing. Replacement and interior remodeling of the windows will continue through mid-July 2026. All areas immediately adjacent to the windows on the interior of the building will be impacted and/or protected. Project managers will move existing fixtures and items away from the windows so that they are a safe distance prior to work beginning.

Campus Community
Monday, May 4 2026 - August 2026

Parking Lot - Repave

Beginning Monday, May 4, 2026 and running through August 2026, portions of the "purple" parking lot (adjacent to the Mehdi Heravi, Ray B West, Lundberg & Shed buildings, will be demolished and repaved as indicated on the attached map. In conjunction with this project, overall parking lot lighting and storm drainage will be improved. Sewer lines serving the Lundberg and Gunshed buildings will be replaced as well, along with a remodeled storm drain line serving the Family Life building. The Facilities project manager and associated contractor will work with individuals and suppliers to access the buildings affected. Some parking will still be available as indicated on the map but may be limited at times due to construction equipment operating in the area.

Parking Lot Repave Map

Aggie Boulevard
Monday, May 4 - Mid August 2026

Road Construction

Beginning Monday, May 4, 2026, phase 2 of construction to 700 North (Aggie Boulevard) will begin. Contractors will begin to mobilize, fence off, and close 700 North beginning at the crosswalk between VSB and the HPER building to Bullen Road (see attached map). Walkways and specific crosswalks may not be available for pedestrian use during construction. Buildings that face 700 North will only have access and egress from the rear and side entry ways. Signs will be placed along fronting entrances and are to be used for emergency exit only. The project will progress from west to east, and sections will be opened as they are completed. Please look for a notification from Connect for temporary bus stop locations. Construction is expected to last from May 4th until mid-August 2026. Pedestrian crossing will only be available at the main mall crosswalk between the VSB and the HPER building and bullen road (see attached).
700 North Road Phase 2 - West Section Logistics Plan

Engineering Lab Building
Monday, June 1 - August, 2026

Construction Notice

Beginning this week renovations will begin on the second-floor restrooms in the Engineering Lab Building. This work will encompass rooms 226 and 296 with construction barriers impacting the hallways but not blocking through access. These restrooms will be closed for the durations of the project; the first-floor restrooms will remail operational. This project is planned for completion in August.

ITS Parking Lot
Tuesday, May 26 - Tuesday, June 9, 2026

Temporary Parking Lot Closure

Due to trenching and utility work as part of the construction of the Administrative Services building, portions of the orange parking lot east of the IT Services building will be inaccessible (please refer to the map document). This parking lot closure will begin on Tuesday, May 26, 2026, at 8:00 AM and will reopen on Tuesday, June 9, 2026. Vehicles will not be able to park in the listed sections of the Orange parking lot during these dates. We do advise you to park in the orange lot just south of the Facilities building.  There will be a pedestrian access gate and bridge over the trench for individuals wanting to access the IT Services building and lobby from the east side.

Logan Campus
Monday, June 1 - Wednesday, June 3, 2026

Elevator Testing

Beginning next week various elevators on campus will undergo their five-year tests. Please see the below list for elevators and the corresponding dates. During this time, the elevator will be unusable and there may be some noise as the testing is done. 

Old Main - Monday, June 1, 2026

Water Lab - Tuesday, June 2, 2026

Forage and Range - Wednesday, June 3, 2026

Hazardous Waste, RACC, and Facilities Greenhouse Buildings
Tuesday June 2, 2026

Electrical Shutdown

On Tuesday June 2, 2026, facilities technicians will be shutting off the power in the buildings from 6:00am to 9:00am in order to repair electrical equipment. Consequently, power will not work during this time.

HPER Building
Tuesday June 2, 2026

Steam Shutdown to Pools

On Tuesday June 2nd, 2026, facilities technicians will be shutting off the steam to the HPER pools from 10:30am to 3:00pm in order to replace a valve. Consequently, the pools won't be heated during this time.

Upcoming

Bioinnovations Building
Thursday June 4, 2026

Generator Testing

On Thursday June 4, 2026, technicians will run testing on the emergency generator between 6:00am-7:00am. Consequently, the power will be switched over to backup power for about ten minutes before switching back over to regular power. This testing should not affect daily operations.