USU Facilities

Facilities serves Utah State University by providing an environment for education, innovative learning, and its application in the worldwide community.

Outages & Shutdowns

Outage and shutdown information is updated as it becomes available. Unless otherwise listed, please call Facilities, Customer Service at 435-797-3535 or 435-797-1947 with any questions or concerns.

Current

BNR Building
Friday, March 27, 2026

Fire Alarm Outage

Scheduled for Friday, March 27, 2026, Facilities technicians will be shutting down fire alarms from 6:30 AM - 8:30 AM at the BNR building. This is necessary so that contractors may complete duct detector testing. We ask that you inform additional people within your departments as needed.

Old Main Building
Friday, March 27 to Monday, April 6, 2026

Old Main A/C Shutdown

On Friday, March 27, 2026, the first phased utility outage to the HVAC system will begin as part of the Old Main re-piping construction project. There will be no access to air-cooling systems throughout the building from March 27, 2026, thru April 6, 2026. Heat will still be available during this first phase of construction. If rooms become too warm, please contact Facilities Customer Service at (435) 797-3535, and HVAC technicians may be able to adjust air flow. These adjustments will only increase air flow, not provide cooling.
The overall project will affect heating and cooling in various areas of the building through the month of August 2026. Additional information will be sent out regarding future utility outages as soon as information is available.

In the 10-day forecast, temperatures are predicted to be lower than the past week or two. We expect this to alleviate the immediate concerns regarding cooling. Looking ahead, every effort is being made to devise alternate methods of cooling, and to minimize utility outages this summer. Additionally, we are currently working to arrange alternate work locations that could be reserved for individuals who cannot work in their offices due to uncomfortable warmth. Details on those options will be forthcoming as they are available

Old Main
March 23 to August 31, 2026

Old Main Construction

The continuance of the Old Main piping replacement project taking place this spring/summer. This project will continue repairs to some of the heating water, and cooling water pipes in the building, as well as the addition of isolation valves for some other plumbing fixtures.  Much of the work will take place in mechanical rooms, pipe chases, and corridor ceilings of the building.  We expect most impacts to the building occupants to be experienced in the corridors, but some departmentally assigned spaces could also be affected.  In addition to construction areas in the corridors, some temporary shutdowns of water, heating, and cooling systems may be necessary. Utility outage notices will be sent out prior to any outage.  Below is a list of impacts to expect during this project.

  • Preparation for the piping replacement will begin on March 23rd.  You will begin to see contractors in the hallways and accessing ceilings.  The following Monday - March 30th, piping replacement will begin in earnest.
  • Construction is planned between March 23rd and August 31st.  
  • Construction will occur mainly in the hallways of the building. This means you may encounter places where part of the hallway is blocked off.  The contractor will maintain access around the work wherever possible.
  • It is possible that doors may be blocked occasionally, if work is taking place overhead.  
  • Construction will move through the building to those locations where the piping needs to be replaced.  Please expect a shifting work site as the project progresses.  Some locations where work can be expected are in the basement and first floor hallways, as well as some piping chase locations that may need to be accessed near your work areas.
  • Please expect construction noise and smells in the building.  This work includes welding and the associated smells. We are doing whatever we can to minimize the disruptions to the building occupants, but due to the extensive nature of this project, some noise and smells will be unavoidable.
  • Air temperature controls in the building will be limited throughout the duration of the project.  It could be cooler than comfortable for some employees, and warmer than comfortable at times.  We are working to limit these impacts as much as possible.

1400 North
Friday, March 20 to Friday, April 24, 2026

Road Construction

Beginning Friday, March 20, 2026, construction on the 1400 North roadway, just adjacent to the new Vet Med Education building will begin. Traffic control signage and traffic barrels will be placed to direct traffic appropriately around the construction limits on the road. There may be traffic delays at times. The estimates completion date for this construction is Friday, April 24, 2026.

Please note that this is not a road closure. There will still be access for all thru traffic.

NEZ
March 3, 2026 to March 31, 2026

Smoke Detector Shutdown

Scheduled from March 3rd to March 31st, 2026 facilities electricians will be disabling the smoke detectors while there is welding in the mechanical rooms. This is necessary so contractors can install chilled water piping.

Upcoming

VSB & LARC Building
Thursday, April 2, 2026

Electrical Shutdown

On Thursday April 2, 2026, facilities technicians will be turning off the power to the building from 6:00am to 7:30am to test the emergency power. Consequently, only e-power will be available in the building during this time.

VSB & LARC Building
Thursday, April 2, 2026

Electrical Shutdown

On Thursday April 2, 2026, facilities technicians will be turning off the power to the building from 6:00am to 7:30am to test the emergency power. Consequently, only e-power will be available in the building during this time.

Engineering Lab
Thursday, April 2, 2026

Fire Sprinkler Shutoff

Scheduled for Thursday, April 2nd, our technicians will be shutting off the Fire sprinkler system at the Engineering Lab from 7am until 8am. This is necessary to relocate the fire sprinkler. There should be little to no effect to building occupants.

USU
Sunday, May 3, 2026 - Sunday, May 10, 2026

2026 Steam Shutdown

This utility shut-off is done to provide necessary maintenance to our steam tunnel/utility systems throughout the USU Logan Campus.

During this week, there will be no steam, hot water, or heat to buildings on the central steam system. Please plan accordingly.